Building – Contract. The Technology and Construction Court, on the claimant developer's CPR Pt 8 claim for declaratory relief, held that the defendant building contractor had had no contractual right to have made or be paid in respect of an application for a further interim payment (or any subsequent application thereafter), in circumstances where the application had been made after the period covered by an agreed schedule governing the making of interim applications and payments.